How to Configure a High Voltage Energy Meter

Edge's load balancing reasons in terms of current at a nominal 230 V per phase. On most sites the grid meter sits on the low-voltage side, so its readings map to 230 V directly. On installations where the metering point is on the medium/high-voltage side of a transformer — or where the meter reads through voltage transformers (VTs) — the measured voltage is not ~230 V and the per-phase current is small. Feeding those raw numbers to the load balancer would give the wrong available current.

The High Voltage (conversion) meter type solves this. It wraps a normal (source) energy meter and presents normalized values to the rest of Edge:

  • Voltage is reported as a fixed 230 V on every phase (a reference, not a measurement).
  • Current per phase is re-derived from the source meter's apparent power, so that 230 V × current reproduces the true apparent power. Because meters expose apparent power only as a total, Edge distributes it across the phases in proportion to each phase's measured current.
  • Active power, reactive power, apparent power and energy (Wh import/export) are passed through from the source meter unchanged.

The result is a meter that behaves like a standard 230 V meter for load balancing, while the underlying device keeps measuring at its real voltage level.

📘

The conversion only normalizes how voltage and current are presented. It does not apply the transformer or CT/VT ratio for you — configure those ratios on the source meter so that its power and energy readings already reflect true primary-side values.

Why this matters — a worked example

Picture a site fed through a 10 kV connection with a 1000 A limit configured in Edge. At a moment when 700 kW is flowing (assume unity power factor, so kW ≈ kVA):

  • Balanced over three phases, that is ~233 kW per phase.
  • The meter sits on the 10 kV side, so the current it actually measures is about 233 kW ÷ 10 kV ≈ 23 A per phase.

If Edge load-balanced on that raw reading, it would compare 23 A against the 1000 A limit, conclude there is roughly 977 A of headroom, and keep ramping up charging — even though the site is already drawing 700 kW.

The High Voltage (conversion) meter normalizes to 230 V, so the same 233 kW per phase becomes:

233 kW ÷ 230 V ≈ 1014 A per phase

Now Edge sees ~1014 A against the 1000 A limit, recognizes there is no headroom, and limits charging correctly. Power and energy are still reported as the true 700 kW — only the voltage/current pair is rescaled so that current-based load balancing is meaningful.

Step 1: Physical Connection

Install and connect the physical energy meter that measures your high-voltage point, following the energy meter installation guide. Set any CT/VT ratios on the meter itself so it reports true power and energy. The meter must be one of the supported energy meters.

Step 2: Add the High Voltage meter in Edge manager

From the Live view, click the + button in the bottom-right corner to add a new energy meter, and select the model High Voltage(conversion).


Step 3: Configure the source meter

Click the new meter to open its dashboard. A Source energy meter section lets you configure the actual physical meter that does the measuring — its model and Modbus connection, exactly as for a standard energy meter.

  • Model — the physical meter model measuring the high-voltage point
  • Protocol — Modbus RTU or Modbus TCP, with the matching interface / address / connection settings
🚧

If no source meter is configured, Edge falls back to a default internal meter profile and readings will not be meaningful. Always configure the source meter that matches your hardware.

Step 4: Validate

Once connected, the Live view shows power flowing and error notifications clear. The meter's voltage reading will show the nominal 230 V per phase by design; the real measured voltages are logged separately (as original voltage L1/L2/L3). Confirm that power and energy match your expectation for the high-voltage point.

Related Articles


Did this page help you?